First Semester Accomplishments:
Concept Generation:
- The team brainstormed project concepts and landed on wheelchair assistive movement (Sep 7, 2020)
- The team created and refined a conceptual prototype (Sep 25, 2020)
CAD Prototype Development:
- The team began designing the prototype and subsystems of the device (Oct 4, 2020)
- The team refined and finalize design for the system prototype model (Dec 6, 2020)
Preliminary Design Report:
- The team created an initial draft for the preliminary design report (Sep 15, 2020)
- The team revised the initial draft of the preliminary design report for submission (Sep 21, 2020)
Initial Project Presentation:
- The team created a presentation detailing the first stages of the project (Sep 20, 2020)
- Carolyn Pye represented the team and presented to the other design teams (Sep 20, 2020)
Design Proposal:
- The team created an initial draft for the Design Proposal (Oct 5, 2020)
- The team revised the initial draft of the Design Proposal for submission (Oct 11, 2020)
Mid-Semester Project Presentation:
- The team created a presentation detailing the progress made to the project up to that point (Oct 18, 2020)
- The team presented to the other design teams (Oct 18, 2020)
Mid-Year Report:
- The team created an initial draft of the Mid-Year Progress Report (Nov 23, 2020)
- The team revised the initial draft of the Mid-Year Progress Report for submission (Dec 3, 2020)
Final Design Presentation:
- The team created an initial draft of the final design presentation discussing the final system design and the team’s progress up until that point (Nov 13, 2020)
- The team revised the initial draft of the final design presentation (Dec 3, 2020)
- The team presented the final design to the other design teams (Dec 3, 2020)
Website Development:
- The team began development for the project website (Sep 27, 2020)
- The team updated the website to include the design proposal and prototype development progress (Oct 25, 2020)
- The team updated the website to update the prototype development and Mid-Year Report (Dec 6, 2020)
Propulsion Subteam Schedule:
- The subteam chose the general placement of the subsystem on the wheelchair (Oct 17, 2020)
- The subteam chose the general placement of the motor on the wheelchair (Oct 28, 2020)
- The subteam chose the transmission as well as performing relevant calculations to decide the optimal motor and battery type (Oct 28, 2020)
- The subteam chose the motor, battery, and motor driver as well as choosing the battery type (Oct 29, 2020)
- The subteam choose the specific placement of the motor and battery (Oct 29, 2020)
- The subteam created CAD models for the motor, transmission, transmission housing, hitch, attachment, wheels, and torque transmitter and performed structural analysis on the model (Dec 1, 2020)
Electro-Mechanical Integration Subteam Schedule:
- The subteam preliminary planning for the subsystem including drafting concept drawings and determining the necessary components of the controller (Oct 10, 2020)
- The subteam chose the general placement of the subsystem on the wheelchair (Oct 13, 2020)
- The subteam chose and purchased the arduino and other components of the controller (Oct 15, 2020)
- The subteam designed the circuit boards necessary for the controller subsystem (Oct 26, 2020)
- The subteam assembled and solder the circuit boards and other components(Nov 4, 2020)
- The subteam began the initial stages of programming the subsystem (Nov 4, 2020)
- The subteam completed the programming of the subsystem (Nov 24, 2020)
- The subteam completed a structural analysis of the subsystem (Dec 7, 2020)
Effort Sensor Subteam Schedule:
- The subteam chose an initial concept for effort sensing (Oct 14, 2020)
- The subteam developed and refine conceptual brainstorming for effort sensing (Oct 16, 2020)
- The subteam drafted conceptual sketches of the subsystem (Oct 22, 2020)
- The subteam chose the placement of the effort sensor on the wheelchair (Oct 22, 2020)
- The subteam chose the effort sensors based on research (Oct 22, 2020)
- The subteam created a CAD model of the effort sensor and performed structual analysis (Oct 28, 2020)
- The subteam ordered components of the subsystem (Oct 24, 2020)
- The subteam began physical prototyping of the conceptual design of the subsystem (Nov 11, 2020)
- The subteam designed the control system (Nov 18, 2020)
- The subteam integrated the effort sensor subsystem into the wheel chair and full system (Nov 20, 2020)
Next Steps:
Interim Plans:
Interviewing and Surveys:
The team will conduct interviews and surveys from wheelchair users and health care professionals to elicit feedback on current designs
Propulsion Subteam:
- Purchase the motor, motor driver, battery, brakes, gears, and stock material (January 15, 2021)
- Determine how we will keep a normal force on the wheel to allow for propulsion of the wheelchair (January 20, 2021)
- Finalize CAD drawings for the attachment, hitch attachment, transmission housing, and battery housing (January 20, 2021)
- 3D print designs to determine if any modifications need to be made (January 20, 2021)
- Redesign any CAD models based on 3D printed prototypes (January 30, 2021)
- Create CAD models for the braking system and lifting mechanism (February 2, 2021)
Electro-Mechanical Integration Subteam:
- Test user interface layout based on the 3D printed prototype (January 5, 2021)
- Finalize CAD drawings for adjustment rods, interface housing, and hinge (January 8, 2021)
- Create alternate CAD files for sheet metal manufacturing of the interface housing (January 8, 2021)
- Finalize complete user interface assembly by combining sub assemblies (January 15, 2021)
- Order the stock metal for the adjustment tubes (February 5, 2021)
- Begin developing our coding approach possibly in the form of a finite state machine (February 5, 2021)
Effort Sensor Subteam:
- Convert the readings from the magnetometer into useful information (January, 16 2021)
- Measure and calculate necessary inputs based on readings from the magnetometer (January 30, 2021)
- Complete physical testing with the prototype in different scenarios (February 28, 2021)
- Build a physical testing apparatus necessary for testing (January 23, 2021)
Next Semester Plans:
Prototype Development:
Physical prototyping will begin next semester.
Propulsion Subteam:
- Manufacture all of the components: attachment, hitch attachment, transmission housing, battery housing, braking system and lifting system (March 15, 2021)
- Test the complete system (April 15, 2021)
- Make improvements as needed (May 15, 2021)
Electro-Mechanical Integration Subteam:
- Complete the open loop controller of system (February 28, 2021)
- Complete ANSYS modeling to determine the strength of the attachment points (February 28, 2021)
- Conduct a heat transfer analysis to determine if a fan or heat sink is required (February 28, 2021)
- Investigate possible waterproofing options (February 28, 2021)
- Test the functionality of the circuit board (March 7, 2021)
- Solder electrical components to the circuit board (March 15, 2021)
- Manufacture and Assemble Components (March 15, 2021)
- Test complete system (April 15, 2021)
- Make improvements as needed (May 15, 2021)
Effort Sensor Subteam:
- Continued testing and refining of data collection (March 7, 2021)
- Development of the architecture of the code as well as finite state machine logic (March 7, 2021)
- Physical integration of subsystem (April 15, 2021)
- Software integration of subsystem (April 15, 2021)
- Test complete system (April 15, 2021)
- Make improvements as needed (May 15, 2021)