| Milestone | Date |
| Safety Plan and Review | before “hands-on” work commences |
| Preliminary Information for Website | 9/29 |
| Progress Presentation | 10/3 |
| Problem Discovery | 10/3 |
| Problem Identification Stakeholder Outreach Complete | 10/18 |
| Specific Problem Identified | 10/20 |
| Functional Requirement Framework Complete | 10/20 |
| Progress Presentation | 10/24 |
| Problem Framing | 10/24 |
| Statement of Individual Goal(s) | 10/24 |
| Specific Stakeholder Definition/Outreach | 10/25 |
| Functional Requirements Fully Identified | 10/24 – 11/22 |
| Progress Presentation | 11/21 |
| Problem Definition | 11/22 |
| Midyear Poster Session | 12/14 |