Milestone | Date |
Safety Plan and Review | before “hands-on” work commences |
Preliminary Information for Website | 9/29 |
Progress Presentation | 10/3 |
Problem Discovery | 10/3 |
Problem Identification Stakeholder Outreach Complete | 10/18 |
Specific Problem Identified | 10/20 |
Functional Requirement Framework Complete | 10/20 |
Progress Presentation | 10/24 |
Problem Framing | 10/24 |
Statement of Individual Goal(s) | 10/24 |
Specific Stakeholder Definition/Outreach | 10/25 |
Functional Requirements Fully Identified | 10/24 – 11/22 |
Progress Presentation | 11/21 |
Problem Definition | 11/22 |
Midyear Poster Session | 12/14 |